Figure B-1. Task Timeline for Project Planning for Web-based Surveys
| Task Timeline for Project Planning | Preparation/Planning | Week 1 | Week 2 | Week 3 | Week 4 | Week 5 | Week 6 |
|---|---|---|---|---|---|---|---|
| Getting Started - Chapter 2 | |||||||
| Determine available resources, project scope, and schedule | X | ||||||
| Decide whether to use an outside vendor (and select vendor) | X | ||||||
| Form a project team | X | ||||||
| Determining Your Data Collection Methods - Chapter 3 | |||||||
| Decide how surveys will be returned (optional) | X | ||||||
| Establish a point of contact in the nursing home | X | ||||||
| Establishing Data Collection Procedures - Chapter 4 | |||||||
| Decide whether to track response through identifiers | X | ||||||
| Assemble survey materials (develop and print materials) | ← | → | |||||
| Publicize and promote the survey | ← | — | — | → | |||
| Send prenotification E-mail | X | ||||||
| * Track responses and calculate preliminary response rates | ← | → | |||||
| * Distribute first reminder (a few days after invitation) | X | ||||||
| * Distribute second reminder | X | ||||||
| * Distribute third reminder/close out data collection | X | ||||||